π The new playground is open and we’d love your feedback on its usability, enjoyment, and safety. Please take a few minutes to fill out our survey.
UPDATE 2023-11-01: The new playground is now open.
UPDATE 2023-09-29: Assembly of the new playground has begun.
UPDATE 2023-09-27: We spoke to John Muller, West Lafayette Parks Director, and he shared some updated information about the park updates:
- There was a snag with the installation team at another job, causing delays for Lincoln Park.
- The Team should come in early next week and begin the assembly.
- Another Team will be installing the PIP (Poured in Place) rubber surface for Lincoln Park sometime after the install.
- Paula R. Woods Park will also be shut down, starting next week, to prep the area for a PIP install as well.
- All work should conclude by the third week in October.
The West Lafayette Parks Department recently removed the existing playground at Lincoln Park to replace it with new equipment.
The neighbors, residents, and park users were not involved in the process of selecting the new equipment.
We made a public records request for the options that the City received, listed below. The Parks Department chose to go with Option Five. Which one do you like best?
More details to come.
Option 01
Option 02
Option 03
Option 04
From the West Lafayette Parks Department: βOption 3 & 4 are the same the only difference is the way it was funded in the quote.β